Legal briefing | |

Long and complex contracts: lessons from case law

Overview

Bespoke and long-term commercial arrangements have a tendency to result in long and complex contracts.  Many customers will be acutely aware that if a supplier under-performs, termination is very much a last resort; as a result, they will often push for more detail in the contract to strengthen their ability to hold the supplier to account.  Suppliers, meanwhile, will often respond by seeking to add their own wording designed to protect their position and limit their exposure.  The resulting agreement can sometimes run to hundreds of pages, including numerous schedules – and case law shows that this length and complexity can create problems of its own.  But as we explain below, there are also various ways in which parties can seek to minimise these risks

Risk 1: the main body of the agreement vs the schedules

Complex, long-term commercial agreements often contain a large number of detailed schedules, but unless there is a "hierarchy clause", the courts will not normally give more weight to the main body of the agreement than the schedules (a "hierarchy clause" might say that in the event of any conflict, the terms of the main body should be given precedence over the schedules). The Supreme Court ruling in MT Hojgaard v E.ON Climate & Renewables (2017) illustrates how this approach can lead to parties being "caught out" by wording that is "hidden away" in a schedule (as opposed to being more prominently set out in the main body). 

The dispute arose after the failure of some offshore wind turbines installed by MT Hojgaard.  The purchaser, E.ON, argued that the foundations of the turbines were subject to a 20-year warranty set out in the Technical Requirements of the project (which formed part of the agreement).  The supplier, MT Hojgaard responded that if the parties had genuinely intended there to be such a significant warranty, it would have been clearly set out in the main body of the agreement, not "hidden away" in a technical annex.  It maintained that the reference to lifespan was only included because the foundations were being constructed to a particular technical standard, based on which the foundations would be expected – but not guaranteed – to last 20 years. That standard ultimately turned out to be flawed, leading to the failure of the wind turbines – but since MT Hojgaard had not developed the standard itself, it argued that it was not directly at fault for that failure. The Court of Appeal agreed, finding that the reference in the schedule was "too slender a thread on which to hang a finding that [MT Hojgaard] gave a warranty of 20 years' life for the foundations."  The Supreme Court, however, ruled that the technical annex was expressed to have contractual effect – and that the wording was also clear enough to give rise to a 20-year warranty (even if, subjectively, this was not what the supplier had intended).  For more discussion of this case, see our detailed briefing.

Main body vs schedules: lessons from case law

Whilst the main body will often be pored over by the parties' legal advisers, schedules won't always get the same level of attention – and some may be drafted without any legal review at all. The danger is that in the event of a dispute, one of the parties may then trawl through the schedules in search of wording that supports its desired position.  A hierarchy clause won't necessarily help because unless the main body is clearly at odds with the wording in the schedule, the courts will normally take the view that there is no conflict – and the wording in the schedule will stand.  In many cases, it may be impractical and/or uncommercial for all schedules to be subject to the same level of detailed review as the main body.  However, there will often be a "middle way", which involves identifying which schedules are particularly important and seeking to ensure that these are subject to at least some level of review, designed to spot any inadvertent "hostages to fortune" in the wording.

Risk 2: internal inconsistencies or mistakes

The longer and more complex the contract, the higher the chance of internal contradictions, inconsistencies or mistakes.  This is well illustrated by Amey v Birmingham City Council (2018), which involved a dispute over an outsourcing agreement for the maintenance of the Council's entire road network.  Amey was struggling to make it profitable and a serious backlog had developed, resulting in numerous potholes going unfilled.  Some of the roads for which the Council was legally responsible were missing from one of the schedules.  Amey argued that this meant that they weren't covered by the agreement and the Council would have to pay extra for maintenance of those roads.  The Court of Appeal disagreed. Having undertaken a close reading of the contract, it concluded that it could – and should – be read in a way which resulted in the roads being covered, despite the omission from the schedule.  But Lord Justice Jackson also had this to say:

Stepping back from the detail, the Court of Appeal's view was that the obvious long-term purpose of the contract was the maintenance of the Council's entire road network; as the majority of the wording was consistent with this, it was appropriate to treat Amey's argument in favour of a narrower, more literal interpretation, with a significant degree of scepticism.

Internal inconsistencies or mistakes: lessons from case law

As the Court of Appeal acknowledged in Amey, the length and complexity of many outsourcing contracts is likely to make it difficult to iron out all internal inconsistencies. Where there is a particular concern that a counterparty may seek to exploit such issues, it may be worth considering the imposition of a general duty of good faith with regard to aspects of the contract which are considered to be of particular importance.  Good faith may prevent "cynical resort to the black letter" of the agreement – or at least assist in pushing back against a very narrow and excessively literal approach to contractual interpretation by the counterparty.  Having said that, any such drafting needs careful consideration; our view is that, generally, a carefully targeted duty is preferable to a very broad, contract-wide duty of good faith (since the latter may have unintended consequences).

Key takeaways

Whilst there are usually perfectly good reasons why many contracts are long and complex documents, case law demonstrates that this can create its own problems. Since eliminating all ambiguity and inconsistency is likely to be impossible parties should instead:

  • avoid focussing largely or exclusively on the main body of the contract and ensure that key schedules are subject to proportionate review; and

  • consider whether good faith or hierarchy clauses in the main body can help to reduce the risk of the counterparty exploiting any drafting ambiguities or inconsistencies that may remain.